How long can concrete stay in a mixer truck? Discharge time on Singapore sites

Wet concrete falling from a black placing hose onto a formwork edge on a sunny construction site
Image by annawaldl from Pixabay Source

How long can concrete stay in a mixer truck?

The short answer depends on the specification, not on the truck. The National Ready Mixed Concrete Association (NRMCA) says in its guide to ready mixed concrete that ASTM C94, the specification most ready-mix is sold under, indicates concrete should be discharged on the job site within 90 minutes and before 300 revolutions after water was added to the cement. NRMCA adds that the purchaser may waive this requirement when conditions permit.

Two points follow from that wording:

  • The clock starts when water meets cement, which is at the batching plant, not when the truck reaches your gate.
  • The 90 minutes is a guideline in an American standard, widely used as a reference point. In Singapore, ready-mixed concrete is supplied by plants certified under BCA's scheme: BCA's supply workhead list shows that workhead SY01B, supply of ready-mixed concrete, requires a Certificate of Conformity issued by SAC. The concrete standard used in Singapore is SS EN 206:2014, and its delivery clauses cover the delivery ticket (7.3) and mix adjustments after main mixing and before discharge (7.5). The mix specification and the supply agreement set the discharge window for your project.

Why does concrete stiffen while it waits?

NRMCA's ordering guide (CIP 31) explains that concrete stays fresh for only a period of time and should be placed and finished within it. It normally sets and hardens within two to eight hours after mixing. Before that, it loses slump, which is the measure of how easily it flows and can be placed.

Slump loss speeds up with heat. NRMCA's hot weather concreting guide (CIP 12) says higher temperatures accelerate slump loss and make concrete set quicker, and that the hot-weather factors of heat, wind and sun can occur at any time, especially in arid or tropical climates. A truck that waits at a Singapore gate in full sun is working against the clock for every minute it idles.

What affects how much time you really have?

FactorEffect on the discharge window
Concrete temperature and weatherHotter concrete loses slump and sets faster (NRMCA CIP 12)
Travel time from the plantUses up part of the window before the truck arrives
Waiting at the gate or on siteEvery minute counts from batching, so queues cost working time
Admixtures in the mixNRMCA notes workability can be designed to last longer, and retarding or extended-set admixtures are used for long deliveries or very high temperatures

Can you add water to loosen the concrete?

Only within limits. NRMCA says water should not be added unless the slump is below what was specified. If water is added, it goes in all at once and the drum is turned a minimum of 30 revolutions, about two minutes, at mixing speed. The amount must not exceed the mixing water set in the mix design: CIP 31 warns that excess water can cause segregation, delay setting, increase the potential for cracking and reduce strength and durability.

CIP 12 goes further for hot conditions and says adding water to concrete that is more than 1½ hours old should be avoided.

Water is not the only fix. NRMCA notes that air-entraining, water-reducing, set-retarding or high-range water-reducing admixtures may be added before discharge to make up for high temperatures or long delivery times, and that the producer will assist the purchaser. Follow the plant's guidance and the agreed spec.

How do you stop a truck waiting on site?

Most delays are on the site side, and they are avoidable:

  1. Be ready before the first truck arrives. CIP 31 says the crew should be ready for placement when the truck arrives, and to tell the producer about any schedule change or work stoppage as soon as it is known.
  2. Match delivery rate to placing rate. Tell the supplier the rate your pump or crew can take, so trucks are not queuing with loads going stiff.
  3. Keep the route clear. Plan the gate, hardstanding and turning space so a loaded mixer can reach the discharge point without stopping. Our site access checklist covers this.
  4. Check the ticket on arrival. Confirm the mix and batch time against the order before discharge. The full pour-day routine is in our ready-mix delivery guide.
  5. Sign and annotate the ticket. CIP 31 says to document any special occurrences on it.

Responsibility matters here too. CIP 31 states the producer is responsible for the specified slump for 30 minutes after the requested time or the truck's arrival, whichever is later, and that the producer cannot be responsible for the quality of concrete if the purchaser is not ready to accept it at the placement location.

How does Vanguard Transport fit in?

Our drivers run the same routes to the same sites every day, so they know the gate, the queue and the discharge point before the drum arrives. That is how we keep trucks moving on Changi Airport Terminal 5, where 16 mixers deliver daily. Our cement mixer trucks carry 9 to 14 m3 per load and work island-wide, each with its Vanguard driver for the length of the contract. Send your site details through the contact page or WhatsApp us.

Frequently asked questions

Is there a legal time limit for concrete in a mixer truck in Singapore?

No single figure applies to every pour. The discharge window is set by the mix specification and the supply agreement for the project, within the delivery rules of SS EN 206. The 90-minute figure comes from ASTM C94 as described by NRMCA and is the usual reference point.

What happens if the concrete is too stiff when the truck arrives?

Do not add water freely. NRMCA says water should be added only if the slump is below specification, all at once, with at least 30 drum revolutions afterwards, and never beyond the mix design's mixing water. The supplier's plant team advises on any adjustment.

Does hot weather shorten the time concrete stays workable?

Yes. NRMCA says higher temperatures accelerate slump loss and make concrete set sooner, and it recommends planning delivery so that trucks can discharge immediately.

Written by the Vanguard Transport team, Singapore. Sources are linked in the text.