What should be ready before the first truck arrives?
A loaded cement mixer or tipper truck cannot be improvised around. The Workplace Safety and Health (WSH) Council's Workplace Traffic Safety Management guidance asks employers to plan traffic from a risk assessment: the transport activities on site, the types of vehicles, traffic rules, road and weather conditions, work schedules and the training of drivers. For a site manager, that turns into six things to settle before deliveries start.
| Check | What to settle |
|---|---|
| Gate and perimeter | One controlled entry point, a fenced boundary |
| Internal route | Marked lanes, speed limits, no sharp or blind bends |
| Pedestrians | Walkways kept separate from vehicle roads |
| Reversing | Eliminated, or planned, marked and supervised |
| Loading or discharge point | Level, firm, well-lit and clearly marked |
| Arrival times | Staggered, so trucks do not queue on the public road |
How should the gate and perimeter work?
The WSH Council's Workplace Traffic Safety Management Guidelines say the perimeter of any workplace using transport vehicles should be fenced to keep out unauthorised access, and people who need to enter should be directed to the appropriate entry points. Traffic routes, storage areas, passageways and pedestrian walkways should be clearly marked with floor lines or traffic and safety signs.
In practice, tell each driver which gate to use, which way the route runs and where to stop for a mixer to discharge or a tipper to tip.
What about the route inside the site?
The guidelines recommend avoiding sharp or blind bends where possible. Where a blind spot cannot be avoided they suggest measures such as convex mirrors, road humps, stop signs, traffic signals, a one-way system or an entry prohibition.
Speed limits should reflect the route layout, the weight and type of load, the road surface and the activity around it, with a lower limit where pedestrians are present. Spilled loads and anything fallen from a vehicle should be removed promptly, and the route kept free of obstruction. Adequate lighting is expected on internal roads, junctions, walkways and loading or unloading bays.
Can a truck avoid reversing on site?
The guidelines say the most effective way to reduce reversing risk is to eliminate it, for example by reorganising the area into a one-way system. Where reversing is unavoidable, the WSH Council lists these measures:
- Planned and marked reversing areas that are visible to drivers and anyone nearby
- Non-essential people kept clear of the area
- Working reversing alarms and visible warning lights
- A trained signaller or banksman when the driver's rear view is compromised and no rear-view aids are available
- Physical barriers or wheel stops at bays where vehicles back up to an edge or structure
A signaller must stay visible to the driver, use a signalling system the driver understands, stand in a safe position and wear a high-visibility vest. If the driver cannot see a single signaller, the guidelines call for two or more, or another alternative.
How do you stop trucks queuing on the road?
Ministry of Transport (MOT) comments on parking space within construction sites say it is impractical to mandate holding space inside sites, and that contractors can deploy traffic marshals and stagger vehicle arrival times. Enforcement action is taken against unauthorised parking along public roads. So the delivery schedule is part of site access: a concrete pour or an earth-removal day planned in staggered slots avoids trucks waiting outside.
What does the ground need to be like?
For loading and unloading, the WSH Council guidance calls for a designated area, with the vehicle parked on firm, level ground and wheel chocks used where appropriate. Its list of measures to prevent vehicles overturning includes not driving on steep slopes, slippery surfaces, soft ground, potholes or uneven terrain, so check the discharge point as well as the road to it.
How Vanguard Transport fits
We supply the truck and a Vanguard driver as one service, allocated to your project for the length of the contract. On a long contract the same trucks and drivers return to the same gate every day, so routes and routines become familiar, as on Changi Airport Terminal 5. Our cement mixer trucks carry 9 to 14 m3 per load and our tipper trucks run up to 51 tonnes gross vehicle weight, so share your gate position, route and discharge point with us at the start. Send your site details through the contact page or WhatsApp us.
Frequently asked questions
Who is responsible for traffic management inside a construction site?
The WSH Council's guidelines set out a workplace traffic management plan that management develops and communicates to all levels of workers, with duties assigned to management and workers under the WSH Act and its regulations.
Do I need a traffic marshal at the gate?
The WSH guidelines call for a trained signaller or banksman for difficult manoeuvres such as unavoidable blind spots and tight bends, and for reversing where the driver's view is compromised. MOT notes that contractors can also use traffic marshals to manage site access.
Can heavy trucks wait on the road outside the site?
Unauthorised parking along public roads is subject to enforcement action, according to MOT. Stagger arrival times so trucks are not left waiting outside.
What should I tell a transport contractor before the first delivery?
The gate to use, the route and speed limits, where to stop or discharge, any reversing arrangement and who to contact on site. Check the WSH Council's pages for current requirements.
Written by the Vanguard Transport team, Singapore. Sources are linked in the text.